Project Description
Optimized Stowage – Maximum Intake
Services
- Stowage plan for maximum intake to secure the order for our customer
- Attendance of loading operations in Jiangyin/China
Scope
- Loading and seafastening of total 91 wind tower sections and accessoires, total freight volume about 39,000 cbm
- Coordination of all parties involved on site
- Ensure safe and smooth operations
Added Value
- Stowage plan was optimized on-site by Solumare on request of portcaptain and vessels command
- Optimized stowage led to optimized weight spreading and seafastening
- The shipowner was of the opinion that the entire amount of cargo could not be stowed on board. We rescheduled the stowage and according to our specifications, the entire cargo was finally accommodated on board. This is how we secured the order for our customer.